Church Farm’s Heads of Terms signed through Adobe Sign, Legals tracked to its critical dates with weekly chasers, exchange and completion, the fees flagged until invoiced.
Actors
Dana Whitfield (Partnerships PM) runs most steps; Sophie Brennan (Land, Central) the land terms and exclusivity; Conor Higgins (Construction) the build terms and the abnormal claim; Eleanor Shaw (Partner) decides a claim above the set value.
Starts at
Church Farm, Rugby (CE-014) at Under Offer: Calder Valley Homes’ offer agreed, Westbrook Construction the preferred contractor at £6,320,000.
Ends at
Completion recorded on 4 Dec 2026 and the Site Completed; each triggered fee stays flagged “not yet invoiced” until someone marks it invoiced.
Step1of21This screen is not drawn yet
1Mark the land and build terms agreed
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Heads of Terms
Starts once the land terms and the build terms are agreed
LandAgreed
Land terms agreed
SBSophie Brennan17 Sep 2026
Calder Valley Homes’ offer, agreed 26 Aug 2026: land £3,640,000
ConstructionAgreed
Build terms agreed
CHConor Higgins18 Sep 2026
Read from Westbrook Construction’s appointed bid: agreed build cost £6,320,000 (1 of 4 bids)
Both gates are marked
The Heads of Terms record can start now.
No Heads of Terms record yet
It is pre-filled from the agreed offer and the agreed build cost once started.
On the Heads of Terms tab Sophie Brennan presses Land terms agreed 1 and sets the date; Conor Higgins presses Build terms agreed 2, which reads Westbrook Construction’s agreed build cost of £6,320,000. Both gate marks show with their name and date, and Start Heads of Terms is enabled.
2Start the Heads of Terms record and record the terms
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Heads of Terms record
Revision 1 · started 21 Sep 2026 by Dana Whitfield
Type
Pre-filled from Calder Valley Homes’ agreed offer of £9,960,000 (land £3,640,000) and Westbrook Construction’s £6,320,000
Design / RMAt Reserved Matters approval · trigger to be confirmed[?Q-005]Speculative£40,000
Total fees £262,000 ÷ package £9,960,000 = 2.6%
Linked to
Agreed offer · Calder Valley Homes£9,960,000 · 26 Aug 2026
Appointed bid · Westbrook Construction£6,320,000 · 1 of 4 bids
Revision 1Every later change is a new revision; the earlier ones are kept
Dana Whitfield presses Start Heads of Terms, picks the Type 1 and completes the Package 2, the Fees 3, the Overage 4, the Conditions 5 and the Exclusivity date 6, pre-filled from Calder Valley Homes’ agreed offer, then presses Save 7. Dana sees revision 1, the active fee streams with the effective fee rate of 2.6%, and the links to the agreed offer and bid.
3Set up exclusivity
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Heads of Terms
Land and Build · revision 1
Draft
Land£3,640,000
Build£6,320,000
Package£9,960,000
Fees£262,000
Effective rate2.6%
Exclusivity date23 Nov
Exclusivity
Not set up yet
Sophie Brennan opens Exclusivity › Set up. The product suggests Standard letter, back-to-back, with the rule that made it; Sophie presses Accept suggestion 1, sets the Start 2 and End 3, adds the Milestones 4 and presses Save 5. Once sent, the period is pending signature.
4Generate and approve the agreements
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Agreements
Each drafted, read and approved before it is sent
Heads of Terms, Church FarmDana Whitfield · drafted from Valere’s template, 23 Sep 2026Draft · no gaps
Exclusivity agreement · Standard letter, back-to-backSophie Brennan · drafted from Valere’s template, 23 Sep 2026Draft · Sophie Brennan to approve
Gaps: none. A required value missing from the record would be listed here, and the draft could not be approved until it is filled.
If the record changes after approval, the approval lapses.
Valere GroupSubject to contract
Heads of Terms
Church Farm, Rugby · CE-014 · Revision 1, draft of 23 Sep 2026
Parties
The Hale family · Calder Valley Homes · Westbrook Construction
Type
Land and Build
Land price
£3,640,000
Build cost
£6,320,000
Package
£9,960,000
Valere fee
£262,000
Overage
Overage at 50% of sales above £13,420,000 GDV
Conditions
Subject to the RP board and the S106 variation
Exclusivity to
23 Nov 2026
Dana Whitfield presses Generate 1 on the Heads of Terms, reads the draft in Valere’s format and presses Approve 2 (or Return for changes); Sophie Brennan does the same for the exclusivity agreement. No required value is missing, so no gap blocks the approval; a change to the record after approval would make it lapse.
5Send for signature through Adobe Sign
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Heads of Terms
Land and Build · revision 1
Approved
Land£3,640,000
Build£6,320,000
Package£9,960,000
Fees£262,000
Effective rate2.6%
Exclusivity date23 Nov
Agreements
Heads of Terms, Church FarmApproved
Exclusivity agreement · Standard letter, back-to-backApproved
Send for signature
Heads of Terms, Church Farm, Rugby, revision 1, approved 24 Sep 2026. Sent through Adobe Sign; the status and the signed copy come back to the Site by themselves.
Signatories
1The Hale familyMargaret Hale · margaret.hale@mailbox.example
2Calder Valley HomesSarah Lomax · sarah.lomax@caldervalley.example
Once sent: “Out for signature” on the agreement, and the Heads of Terms becomes issued.
Dana Whitfield presses Send for signature, checks the Signatories 1 (The Hale family, Calder Valley Homes, Westbrook Construction) and presses Send 2; Sophie Brennan does the same for the exclusivity agreement. Each agreement then reads “Out for signature” and the Heads of Terms is issued.
6System: signed, filed, Legals opens
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Stages
Each move is set by the event its module records
Lead10 stages done
Instructed3 Aug
Acceptable Offer26 Aug
Acceptable Build14 Sep
Under Offer14 Sep
LegalsSince 5 Oct
Exchanged
Completed
Heads of Terms, Church FarmSigned
Sent25 Sep 2026To 3 signatories through Adobe Sign
Signed by all5 Oct 2026The Hale family, Calder Valley Homes, Westbrook Construction
Signed copy filed5 Oct 20265 Heads of Terms/Heads of Terms, Church Farm, signed 5 Oct 2026.pdf
Base for variance5 Oct 2026Variance is measured against this copy
Status returned by Adobe Sign; nothing was typed by hand.
ExclusivityActive
Standard letter, back-to-back · 5 Oct to 23 Nov 2026 · signed copy filed to 5 Heads of Terms
HoTs to exchange
100days left
Started 5 Oct · by 13 Jan 2027Under 100 days
Sent to Land, Partnerships and Construction
Church Farm, Rugby moved to Legals: Heads of Terms signed 5 Oct 2026
SBSophie BrennanLand
DWDana WhitfieldPartnerships
CHConor HigginsConstruction
On 5 Oct 2026 Adobe Sign returned the signed copies. The system filed them to the Site’s 5 Heads of Terms folder, marked the Heads of Terms signed and the exclusivity active, moved the Site to Legals, started the 100-day HoTs-to-exchange clock and notified Land, Partnerships and Construction.
7Set the critical dates and the trackers
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
Critical dates set 6 Oct 2026: exchange 13 Nov, completion 4 Dec, longstop 18 Dec, RP board 12 Nov
ExchangeTarget
4days left
13 NovMoved once
CompletionTarget
25days left
4 DecSet 5 Oct
LongstopHard date
39days left
18 DecIn the contract
HoTs to exchange
65days left
13 JanDay 35 of 100
Oldest outstanding
Land contract draft
With Hadley & Finch LLP for 21 days · critical, 14 days late
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
21
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
12
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
4
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
On Legals Dana Whitfield presses Set dates 1 for exchange (Fri 13 Nov), completion (4 Dec), longstop (18 Dec) and the RP board (12 Nov), uses Add milestone 2 and Add document 3, and Update 4 as a document passes. Dana sees a countdown per date, the progress tracker with days per holder, the critical items, contracts out, and the oldest outstanding item: the land contract draft, with Hadley & Finch LLP for 21 days.
8System: weekly chasers and updates are drafted
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
Drafts for the week of Mon 9 Nov
4 drafts · from Dana Whitfield’s mailbox
Solicitor chaserAlex Rowan · Hadley & Finch LLPChurch Farm, Rugby: open items this weekAwaiting approval
Board-date chaserSarah Lomax · Calder Valley HomesChurch Farm: your board paper for 12 NovemberAwaiting approval
Weekly update, RPSarah Lomax · Calder Valley HomesChurch Farm: progress this weekAwaiting approval
Weekly update, landownerMargaret Hale · The Hale familyChurch Farm: where things standAwaiting approval
Drafting day and the days without contact are not set yet[?Q-016]
ExchangeTarget
4days left
13 NovMoved once
CompletionTarget
25days left
4 DecSet 5 Oct
LongstopHard date
39days left
18 DecIn the contract
HoTs to exchange
65days left
13 JanDay 35 of 100
Oldest outstanding
Land contract draft
With Hadley & Finch LLP for 21 days · critical, 14 days late
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
21
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
12
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
4
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
4 drafts readyChurch Farm, Rugby: chasers and weekly updates for the week of Mon 9 Nov, drafted 07:00
For the week of Mon 9 Nov the system drafted a chaser to Hadley & Finch LLP, a board-date chaser to Calder Valley Homes for 12 Nov, and a weekly update each for the RP and the landowner, and told Dana Whitfield the 4 drafts are ready; they are listed on the Legals tab.
9Review and send the chasers
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
Drafts for the week of Mon 9 Nov
4 drafts · from Dana Whitfield’s mailbox
Solicitor chaserAlex Rowan · Hadley & Finch LLPChurch Farm, Rugby: open items this weekAwaiting approval
Board-date chaserSarah Lomax · Calder Valley HomesChurch Farm: your board paper for 12 NovemberAwaiting approval
Weekly update, RPSarah Lomax · Calder Valley HomesChurch Farm: progress this weekAwaiting approval
Weekly update, landownerMargaret Hale · The Hale familyChurch Farm: where things standAwaiting approval
Drafting day and the days without contact are not set yet[?Q-016]
ExchangeTarget
4days left
13 NovMoved once
CompletionTarget
25days left
4 DecSet 5 Oct
LongstopHard date
39days left
18 DecIn the contract
HoTs to exchange
65days left
13 JanDay 35 of 100
Oldest outstanding
Land contract draft
With Hadley & Finch LLP for 21 days · critical, 14 days late
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
21
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
12
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
4
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
Dana Whitfield opens each draft, uses Edit 1 on the wording or the recipients (or Drop to discard one) and presses Approve and send 2. Each email goes from Dana’s own mailbox and is logged on the Site; the solicitor chaser carries no opt-out line, and the landowner update can go because The Hale family’s consent to email is recorded.
10Decide the abnormal cost claim and read the variance
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Change and abnormal log
Claims above £50,000 go to a Partner / MD (admin-set value)
ESEleanor ShawFinance partner · approver above the set value
Approved by Eleanor Shaw, 28 Oct 2026: the change log, the package, the fee and each party’s exposure follow the approved amount
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Build +£74,000: the approved abnormal claim
Westbrook Construction submitted Valere’s Abnormal Build Cost Claim; Conor Higgins presses Record claim 1 and enters the change type, the initiator, the evidence and the original and revised breakdowns. It is above £50,000, so Eleanor Shaw is named and presses Approve 2. The variance then reads build £6,320,000 → £6,394,000 and package £9,960,000 → £10,034,000; land and fee have no change.
11Record exchange
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
ExchangeTarget
4days left
13 NovMoved once
CompletionTarget
25days left
4 DecSet 5 Oct
LongstopHard date
39days left
18 DecIn the contract
HoTs to exchange
65days left
13 JanDay 35 of 100
Oldest outstanding
Land contract draft
With Hadley & Finch LLP for 21 days · critical, 14 days late
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
21
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
12
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
4
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
Record exchange
Church Farm, Rugby: enter the exchange date and the final values.
Exchange date
Final land
£
Final build
£
Final fee
£
On confirm
The Site moves to Exchanged
The Fee and Heads of Terms values are revised from these figures
The exchange milestone closes on its own
Triggered: Agency fee (RP), at exchange · £130,000
When contracts exchange Dana Whitfield presses Record exchange, enters the date 1 and the final land, build and fee values 2, and presses Confirm 3. The Site is at Exchanged, the Fee and Heads of Terms values are revised from the figures entered, the exchange milestone closes on its own, and the fees whose trigger occurred show as triggered.
12Record completion; fees flagged until invoiced
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
CompletedLand & BuildClosed record · read-onlyTriggered fee not yet invoicedLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Stages
Each move is set by the event its module records
Lead10 stages done
Instructed3 Aug
Acceptable Offer26 Aug
Acceptable Build14 Sep
Under Offer14 Sep
Legals
Exchanged13 Nov
Completed4 Dec
Completion
Recorded by Dana Whitfield
Completed
4 Dec 2026
Final land
£3,640,000
Final build
£6,394,000
Final fee
£262,000
Legals readiness
Milestones complete
Fee invoice raised: 1 of 2 triggered fees
Each triggered fee with no invoice keeps its flag on the Site and in Legals’ weekly controls until it is marked invoiced, even after completion.
Fees
Fee agreement signed 3 Aug
Agency fee (RP)
Invoiced
£130,000Agreed
Trigger
At exchange
Triggered13 Nov
Invoiced16 Nov
Overage
Not triggered
£20,000Contingent
Trigger
At the overage event
Triggered
Invoiced
Contractor introduction
Triggered
£72,000Agreed
Trigger
At JCT signing · 50/50 split
Triggered13 Nov
Invoiced
Triggered fee not yet invoiced
Invoice date
Design / RM
Not triggered
£40,000Speculative
Trigger
At Reserved Matters approval · trigger to be confirmed[?Q-005]
Triggered
Invoiced
Dana Whitfield presses Record completion, enters the final values 1 and confirms; later, on Fees, Dana sets the invoice date 2 and presses Mark invoiced 3 on each triggered fee. The Site is Completed, a closed record; the contractor introduction fee keeps “Triggered fee not yet invoiced” until it is marked invoiced, even after completion.
13Alternative: an agreement is declined in Adobe Sign
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Heads of Terms
Land and Build · revision 1
Issued
Land£3,640,000
Build£6,320,000
Package£9,960,000
Fees£262,000
Effective rate2.6%
Exclusivity date23 Nov
Heads of Terms, Church FarmNot signed
Sent25 Sep 2026To 3 signatories through Adobe Sign
Declined by Westbrook Construction, 29 Sep 2026Returned by Adobe Sign
Signed copyNot filed
Revise makes revision 2, generated and approved again
Next action
Raised for the sender
Revise or resend the Heads of TermsPartnershipsToday
A declined fee agreement would also notify Partners / MD.
Alternative: Adobe Sign returned the Heads of Terms as declined by Westbrook Construction on 29 Sep 2026; the sender is notified and given a Next Action. Dana Whitfield chooses Revise 1 (a new revision, generated and approved again) or Resend 2.
14Alternative: the Adobe Sign connection is not set up
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Heads of Terms
Land and Build · revision 1
Approved
Land£3,640,000
Build£6,320,000
Package£9,960,000
Fees£262,000
Effective rate2.6%
Exclusivity date23 Nov
Agreements
Heads of Terms, Church FarmApproved
Exclusivity agreement · Standard letter, back-to-backApproved
Adobe Sign is not connectedSending is blocked: the Adobe Sign connection is not set up or was refused. Tom Ashworth (Admin) has been told. The draft stays approved.
Alternative: Dana Whitfield presses Send for signature 1, but the Adobe Sign connection is not set up or was refused. Sending is blocked with an error that names the connection, the admin is told, and the draft stays approved.
15Alternative: a critical date slipping
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighStalled: critical Legals task past deadlineLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
System entry in Activity, Fri 6 Nov 2026: counts as a legal blocker on the Friday Legals view and the MD’s exceptions
ExchangeTarget
4days left
13 NovMoved once
CompletionTarget
25days left
4 DecSet 5 Oct
LongstopHard date
39days left
18 DecIn the contract
HoTs to exchange
65days left
13 JanDay 35 of 100
Critical path · 14 days late
Oldest outstanding
Land contract draft
With Hadley & Finch LLP for 21 days · critical, 14 days late
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
21
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
12
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
4
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
Stall alert: Church Farm Valere CRM <notifications@valere.example> → Dana Whitfield <dana.whitfield@valere.example>
Valere CRMNotification
Stall alert
Church Farm has stalled
Stalled: critical Legals task past deadline.
CE-014Church Farm, Rugby
Legals
Deal Health
55
Deadline was
Mon 26 Oct 2026
Late
11 days
Task
Land contract draft, with Hadley & Finch LLP for 18 days · critical path
Rule
Critical Legals task past its deadline (threshold set by Admin) [?Q-002]
You get one alert when the rule starts, not one a day, and Rhys Calloway has been told as MD.
Open Church FarmSee why the rule fired
You received this because you own the Site.
Notification settings·Open Valere CRM
Valere CRM · from the Valere notification mailbox, only to Valere staff
Alternative: the land contract draft is past its deadline of 26 Oct 2026 on the critical path, so the Site shows “Stalled: critical Legals task past deadline”, a system entry is written on Fri 6 Nov 2026, and the stall letter reaches Dana Whitfield with the MD told. Dana presses Update 1 and sets a new holder 2, a moved deadline 3 with the original kept, or a note 4.
16Alternative: the longstop date passes
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
Mon 21 Dec 2026: the longstop of Fri 18 Dec 2026 has passedDana Whitfield has a Next Action and the Site counts as a legal blocker; with exchange and completion passed too, the one notification names the longstop. Set a new longstop with its reason, or decide to close the Site. The earlier longstop stays in the history.
ExchangeTarget
38days overdue
13 NovMoved once
CompletionTarget
17days overdue
4 DecSet 5 Oct
LongstopHard date
3days overdue
18 DecIn the contract
HoTs to exchange
23days left
13 JanDay 77 of 100
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
21
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
12
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
4
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
Alternative: on Mon 21 Dec 2026 the longstop of Fri 18 Dec 2026 has passed. Dana Whitfield is notified and given a Next Action, and the Site counts as a legal blocker; every countdown reads overdue in red. Dana presses New longstop 1 with its reason, or Close Site 2; the earlier longstop stays in the history.
17Alternative: exclusivity ends in 14 days
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Exclusivity
Standard letter, back-to-back · to 23 Nov 2026
14 days left · extension letter drafted for Land
Extension letter · end date 23 Nov 2026 → 18 Dec 2026Drafted 9 Nov 2026 from Valere’s templateAwaiting approval
Once it is signed, the end date moves. If it is not signed by the end date, the period becomes ended and the owner is notified.
Next action
Approve the extension letterLandToday
Exclusivity on Church Farm ends in 14 days Valere CRM <notifications@valere.example> → Sophie Brennan <sophie.brennan@valere.example>
Valere CRMNotification
Exclusivity ending
Exclusivity on Church Farm ends in 14 days
It ends on Mon 23 Nov 2026.
CE-014Church Farm, Rugby
Legals
Ends
Mon 23 Nov 2026
Left
14 days
Fee
£262,000
Exclusivity on Church Farm, Rugby ends on Mon 23 Nov 2026. An extension letter to Fri 18 Dec 2026 is drafted for you. You will be told again if it ends.
Open Church FarmOpen Heads of Terms
You received this because Heads of Terms and Exclusivity names you on this Site. Your cover is told while you are out of office.
Notification settings·Open Valere CRM
Valere CRM · from the Valere notification mailbox, only to Valere staff
Alternative: exclusivity ends on 23 Nov 2026. Sophie is notified with the exclusivity letter and a Next Action, and the extension letter to 18 Dec 2026 is already drafted; Sophie Brennan presses Approve 1, then Send for signature 2. Once signed, the end date moves; unsigned by the end date, the period becomes ended.
18Alternative: the claim needs more, or has no approver
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Change and abnormal log
Claims above £50,000 go to a Partner / MD (admin-set value)
ESEleanor ShawFinance partner · approver above the set value
Decision history
More information, Eleanor Shaw: the claim stays open
A later decision is a new entry; this one is kept. A claim approved in part counts only the approved amount in the variance.
Above the set value with no Partner / MD named
No Partner / MD namedThe claim is above £50,000, so the decision cannot be recorded until an approver is named.
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,320,000
No change
Package
£9,960,000
£9,960,000
No change
Valere fee
£262,000
£262,000
No change
Claim: no cost effect until it is decided
Alternative: Eleanor Shaw presses More information 1 and the claim stays open, with no cost effect until it is decided; a later decision is a new entry and this one is kept. Above £50,000 with no Partner / MD named, the decision cannot be recorded.
19Alternative: an email proposes a legal date
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
ExchangeTarget
1days left
13 NovMoved once
CompletionTarget
22days left
4 DecSet 5 Oct
LongstopHard date
36days left
18 DecIn the contract
HoTs to exchange
62days left
13 JanDay 38 of 100
Oldest outstanding
Land contract draft
With Hadley & Finch LLP for 24 days · critical, 17 days late
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
24
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
15
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
7
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Proposed update
Proposed
Board approval, first roundOpenApproved 12 Nov 2026
Sarah Lomax, Calder Valley Homes: “Our board approved Church Farm today.”
Nothing changes until you accept it; the email stays linked.
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
A proposed update on Church Farm is waiting for you Valere CRM <notifications@valere.example> → Dana Whitfield <dana.whitfield@valere.example>
Valere CRMNotification
Proposed update
A proposed update is waiting
One change, read from an email. Nothing changes until you accept it.
CE-014Church Farm, Rugby
Legals
Milestone
Board approval, first round
Proposed
Approved Thu 12 Nov 2026
Source
Email from Sarah Lomax, Calder Valley Homes, Thu 12 Nov 2026
Quote
“Our board approved Church Farm today.”
Valere CRM read an email from Calder Valley Homes and proposes one change to Church Farm, Rugby. Look at it beside the email, then accept or discard it.
Review the proposed updateOpen the source email
You received this because you own the Site. Nothing on it changes until you accept.
Notification settings·Open Valere CRM
Valere CRM · from the Valere notification mailbox, only to Valere staff
Alternative: Sarah Lomax of Calder Valley Homes writes that its board approved on 12 Nov 2026. On that day the proposed update shows on the board approval milestone with the email linked, and the proposed update letter reaches Dana Whitfield; nothing changes until Dana presses Accept 1, or Discard 2.
20Alternative: exchange with items still open
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
LegalsLand & BuildPriority: HighLegals is owned jointly byLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
StatusActive
Construction InvolvedYes
Deal HealthFairProvisional formula
ExchangeTarget
4days left
13 NovMoved once
CompletionTarget
25days left
4 DecSet 5 Oct
LongstopHard date
39days left
18 DecIn the contract
HoTs to exchange
65days left
13 JanDay 35 of 100
Oldest outstanding
Land contract draft
With Hadley & Finch LLP for 21 days · critical, 14 days late
Variance against Heads of Terms
HoTs signed 5 Oct
Item
Heads of Terms
Now
Change
Land price
£3,640,000
£3,640,000
No change
Build cost
£6,320,000
£6,394,000
+£74,000 (1.2%)
Package
£9,960,000
£10,034,000
+£74,000 (0.7%)
Valere fee
£262,000
£262,000
No change
Critical items
Land · Build · Scheme
Land
Land contract14 days late
Easement enquiry12 days open
Build
JCT amendments2 days late
ProposalsDue 11 Nov
Scheme
S106 variationBlocked: council
Condition 9Due 16 Nov
Fee controls
No fee flag up
Fee agreementSigned 3 Aug 2026
Triggered, not invoicedNone yet · agency at exchange
Exclusivity ends 23 NovExtension letter drafted
Legal progress
5 of 11 closed · 4 critical open · board dates 12 and 20 Nov
Milestone
Held by
Days
Deadline
Status
Heads of Terms agreed
Valere
–
5 Oct
Closed
Land contract draftCritical path
Hadley & Finch LLP
21
26 Oct
In progress
Contractor’s ProposalsCritical path
Westbrook Construction
12
11 Nov
In progress
Board approval, first roundCritical path
Calder Valley Homes
4
12 Nov
Open
ExchangeCritical path
All parties
–
13 Nov
Open
Contracts out
3 with others · weekly chaser to the solicitor drafted today
Document
With
Since
Days
Status
Land contract
Hadley & Finch LLP
19 Oct
21
Draft awaited
Development agreement
Calder Valley Homes’ solicitors
2 Nov
7
Draft
JCT contract
Westbrook Construction
28 Oct
12
Draft
Record exchange
Church Farm, Rugby: enter the exchange date and the final values.
6 critical items are still open
LandLand contract14 days late
LandEasement enquiry12 days open
BuildJCT amendments2 days late
BuildProposalsDue 11 Nov
SchemeS106 variationBlocked: council
SchemeCondition 9Due 16 Nov
A missing fee agreement or an uninvoiced fee would be listed here too. This warns and does not block; continuing is written to the audit log.
Exchange date
Final land
£
Final build
£
Final fee
£
On confirm
The Site moves to Exchanged
The Fee and Heads of Terms values are revised from these figures
The exchange milestone closes on its own
Triggered: Agency fee (RP), at exchange · £130,000
Alternative: at Record exchange the product warns about the open critical items; it warns and does not block. Dana Whitfield presses Continue 1, and continuing is written to the audit log.
21Alternative: system, Heads of Terms open too long
Updated 12m agoJMCHRC
CE-014
Church Farm, Rugby
Under OfferLand & BuildStalled: Heads of Terms open over 30 daysLandPartnershipsConstruction
LandownerThe Hale family
LandSBSophie Brennan
Partnerships PMDWDana Whitfield
ConstructionCHConor Higgins
Region · unitsCentral· 28
Construction InvolvedYes
Valere fee£262,000
Heads of Terms
Land and Build · revision 1
Issued
Land£3,640,000
Build£6,320,000
Package£9,960,000
Fees£262,000
Effective rate2.6%
Exclusivity date23 Nov
Agreements
Heads of Terms, Church FarmOut for signature
Exclusivity agreement · Standard letter, back-to-backOut for signature
Stall rule: Heads of Terms issued and unsignedOut for signature since Fri 25 Sep 2026: open 31 days on Mon 26 Oct 2026. Rule “HoTs open over 30 days” · threshold 30 d, seeded from the sources, not changed since; the Admin can edit it [?Q-002].
Activity
SystemStall rule · Mon 26 Oct 2026
Church Farm, Rugby flagged stalled: Heads of Terms open over 30 days, threshold 30 d
Alternative: the Heads of Terms stayed issued and unsigned beyond the 30-day stall threshold, so on Mon 26 Oct 2026 the stall rules flagged the Site as stalled and wrote a system activity; the badge names the rule, the alert the threshold applied.